Three Hundred Thousand Square Metres, and the Doors Decided It.

A warehousing park in Hebei: 300,000 m² of warehouse on 18,000 Mts of steel, handling 500,000 parcels a day. Docks, ramps and door counts set the building before span did, and the roof stayed clear for the conveyor.

300,000 m²of warehouse
18,000 Mtsof steel
500,000parcels a day
DemonstrationHebei provincial project
The difficulty

A Building Measured in Doors, Not Metres

Storage is the easy half. The other half is every parcel arriving at the same twelve doors between seven and nine in the morning.

01

The door line

Every door is an opening, a canopy, a ramp and a traffic conflict at once. The wall that holds them sets where the columns cannot go, and the columns set the steel.

02

The roof is already spoken for

The conveyor runs under it. Whatever the roof has to carry, and whatever space it must leave, is decided before the purlin spacing is drawn — not after the conveyor arrives.

03

The floor never rests

Half a million parcels a day is not a load, it is a frequency. Slab, joints and surface are chosen for the traffic rather than for the tonnage.

04

It has to look like a demonstration

A provincial demonstration project is visited, photographed and audited. Finishing and consistency become part of the specification.

JD warehousing park, Hebei
JD warehousing park, Hebei — 300,000 m² on 18,000 Mts of steel, 500,000 parcels a day.
What it takes

Six Decisions That Belong Before the Layout

Change any of them after the slab is poured and the cost is no longer in the steel.

01

Count the doors first

Doors, dock levellers and ramps are planned as a line, then the bays are sized around them. Doing it the other way round produces a warehouse with a column in a door.

02

Reserve the roof zone

Conveyor, sprinkler mains and ducting get a corridor in the model. The structure is designed to leave it, not to be cut for it.

03

Design the floor for frequency

Joints placed where traffic runs, and a surface that will still take a pallet when the tenth truck of the morning has crossed it.

04

Plan the yard with the building

Turning circles for the largest trailer that will really arrive decide the setback of the dock face.

05

Settle the fire strategy early

Sprinkler depth is a structural dimension. Discovering it late changes the eave height and the cladding order.

06

Repeat the bay

A park is the same bay many times. Get one right in the model and the rest follow from it — get it wrong and the error repeats at the same scale.

More

Other Cases and the Full Register

Send the Flow Diagram. We Will Tell You How Many Doors It Needs.

Inbound, outbound, peak hour and the largest vehicle. Four numbers, and the layout starts to design itself.

Send the flow